Tcode To Maintain Scheduling Agreement

iam Ag Planning Creation with LPDocument r LPA if I in the delivary calendar in ME38 Shedules r as this 1.02.2007 5.02.2007 6.02.2007 these Shedules are there, but the customer`s demand today is that they need silverly material for production or some factories to repai etchow that matreial before the delivery date delivery schedule is 01.02.2007 but company need to mate on today means 31.01.2007, as you do or retively that Materail please tell me that I do not need e/W for this post. I don`t know what message. BTW, I have another problem. I have 100 Qty in my SA. I kept the delivery plan with 100 Qty. Then the GR led with 100 Qty. I only tried it for regular orders, not for schedulingagrement. Please try to tell us if it doesn`t work. I have successfully established an “LPA” delivery plan (SA) and have assigned a few delivery plans. Well, how to make the real quantities planned to see how much I received.

Basically, I can`t link my SA to an order, maybe I`m following the wrong process. Please help For the calendar agreement, we create the lines of… it`s nothing but bypassing the PO… The framework agreement is a long-term sales contract between Kreditor and Debitor. The structure agreement are two types: www.sap-img.com/materials/what-is-outline-and-scheduling-agreement.htm I have established the planning agreement.in the middle of the agreement, I want to prevent the lender coz from any reason of delivery is not on time.so I created EO for another creditor with the same item of delivery plan. The problem is that the OP is created, but I can`t release it. What for? You want someone to tell me how to authorize the GR against the schedu-ling agreement, Before the date indicated in the rankings, (without calendar lines changed) -0ACheers,0AAMahesh There is another solution, if you do not want to cancel the date of the original schedule only: Hello, if I prepare a delivery plan and put a delivery plan in it, I understand that delivery may be possible from that date. however, it is possible to limit delivery to the only date indicated in the calendar and not thereafter. If so, how? Ideas would be useful MN11 SAP tcode for – Change Message: Schd.

Agmt. Schedule Against a Contract (ME31K), we create a release Oder (by me21 tcode) Have you done ME38 according to ME32L? You can receive the goods on ME38. If we establish a delivery plan, we should meet the quantit y target (z.B. 20 we fill 100), but if we maintain the delivery plan of the provision, it seems to be 20 that the provision does not comply with the quantity controls…… In my case althhough, it was indicated that the target amount of 100, the programming could use the SA article – 20 amount of schedule greater than 100; in my case, the SA was scheduled for 15-0 although 20, the target amount was 100.